MEP Anchor Point Layout for Kiewit
2101 Pts
MEP anchors marked
525 Pts/ Day
Layout productivity
9500 SQF
Project Area

CONTRACTOR
Kiewit
PROJECT
Rail Transportation MEP outdoor Layout
TRADE
MEP

MEP Anchor Point Layout Project
Kiewit Canada used LightYX on a Rail Transportation Line Extension project for MEP anchor point layout on a flat deck. The scope included projecting and marking thousands of anchor points across a 9,500 sq. ft. area.
Using the LightYX BeamerOne system, the team was able to bring the digital layout directly to the field and project MEP anchor locations onto the slab. This allowed the crew to move through the layout work much faster than a conventional total station workflow, especially for a dense point layout with more than 2,000 anchors.
Layout Productivity Results
LightYX helped Kiewit Canada complete 2,101 MEP anchor points in 4 days with a 1-person crew, averaging 525 points per day.
The customer highlighted the time difference compared with conventional total station layout, explaining that the same thousands of points could take months using the traditional workflow, while LightYX reduced the work to a matter of days.

PLEASE FILL IN YOUR
CONTACT DETAILS

DO YOU WANT TO SEE THE SAME RESULTS ON YOUR PROJECT? TRY US
Share a bit of information, and we'll connect you with a LightYX expert to explore our offerings. Discover how the LightYX platform can seamlessly integrate into your workflow for enhanced efficiency and precision

-Photoroom.avif)